Quick update on the luxury boutique “H Hotel” in Barbados for January 2013

This update covers the work through hd studio (formerly Harlequin Developments) that took place before the Christmas/New Year break in 2012 and from 7th to 11th January 2013. Text in red denotes the latest work from January.

– Block A
- Grouting of exterior joints complete
- Screeding to 4th and 5th floors complete
- Block walls to ground floor 98% complete
- Wall lining to Mock UP room commenced

– Block B
- Piling of North Foundation upgrade and walkway foundation complete
- Earthing/grounding of all plunge pools complete

– Block C
- Installation of services to 2nd floor slab complete
- Concrete to 2nd floor slab complete
- Advance decking to 3rd floor South is 98% complete
- Beams installed for rebar installation to 3rd floor South
- Production of stair case commencing
- Advance columns and beams around staircase commencing
- Precast stair case completed for installation
– Ground floor slab structural preparations for installation of stair case in progress
 - Form work fabrication for deck of 1st floor stair surround
– Fabrication of columns to deck of stair surround

– Block D
- Back filling to bays complete
- Excavation for under-slab services to kitchen in progress
- Advance foundation of plunge pools in progress
- North wall modifications in progress

o Block E
- Installation of all services to GF slab complete
- Batteboards for foundation layout in progress
– Jack hammer and clear foundation pile caps
– Fabricate reinforcement for foundation cages
– Excavate and clear foundation pads for blinding